Case Study

9 Town House Development Clapham

Building Structure - Construction Design - Steel Frame Building -Design Tools - Building - LGSS

Selected by Ammonite Projects Ltd to provide a solution whereby the LGSS Engineered Foundation Solution eliminated 50t of excavated soil from being taken off site, 40 HGV deliveries to site and could be constructed without the need for a crane was achieved by the Team.

The JPSE team have completed Robins Court 9 dwelling – 4 storey Town House development in Clapham

JPSE installed 44No. 10m long ScrewPiles with twin foundation beams in week 1. The Insulated Ground Floor and 4 storey structure was installed in 7 weeks.